Afvalstoffen Terminal Moerdijk REFRACTORY INSTALLATION AFTERBURNER

  • Duration Three months
  • Segment Heavy industries, International contractors
  • Oplossing Shotcrete application and refractory gunning

A new incinerator installation was treated with a refractory shotcrete material.

SOLUTION

Quickly and effectively applying 1,400 tonnes of refractory shotcrete material requires special techniques. Shotcrete application is highly suitable for this type of projects.
VTG treated the new incinerator at ATM with a layer of high-quality, refractory shotcrete material. With a production speed of 50 to 110 tonnes per shift, this enormous amount of concrete was sprayed at an incredible speed. The incinerator can now be reliably used for the years to come. The project video below shows the full scope of this project.